Construction on phase 1 at The Yorkdale Condominiums continues to progress as the 11th floor is currently being poured.  Roof topping is estimated for later in November with the commencement of window installation by the end of the year.

1

2

Above is a view looking east from Flemington Road.  At the base are the two storey suites.

4

The retail spaces underneath a large structural concrete canopy along Ranee Avenue can be seen above.

5

 

6

Above is a view looking south west across the Allen Expressway.  Phase 1 is nearing its full height in the back ground with Phase 2 now hoarded off in the foreground as shoring and excavation have commenced.