Construction progress at Queen Ashbridge continues to move along nicely and we have now poured the 12th floor of the condo tower! The Queen Street facade is also fully formed and the amenities roof deck is substantially complete.
Windows and wall panels are now going in on the second floor and will begin climbing up the tower in the New Year. As the concrete climbs, the building is beginning to terrace back with roof topping scheduled for Spring 2024.
The courtyard is substantially complete and is currently being used for a staging ground for many of the construction materials being lifted by the cranes and the northwest crane will be dismantled and removed from site soon.
Interior spaces are also beginning to take shape. The double height gym can be seen above and is waiting for the dramatic south facing glass to be installed.
Stay tuned for more construction updates in the New Year and have safe and happy holidays!